Based on the following payment terms and conditions
Example of payment schedule:
- 10% non refundable deposit to schedule the project, due at the time this contract is signed. In the event that JC Remodeling and Construction LLC cancel this project such deposit will be refunded in full.
- 10% due the first date of the project when demolition starts.
- 20% after new foundation block wall is finished.
- 10% After framing of new walls and roof.
- 10% due after plumbing, HVAC and electrical rough inspection is completed.
- 20% due after tile installation for both bathrooms and kitchen is completed.
- 5% due after drywall and trim is ready for paint.
- 5% once interior/exterior painting is completed.
- 10% due upon completion and customer approval.
- In the event of a default, interest shall accrue from the date of the default at the highest rate allowed by law. Customer agrees to pay all necessary costs, expenses, legal fees and amounts due if this account is tendered for collection.
- All change orders must be paid in advance.
- Except as agreed upon in the contract, replacement or installation of anything not described or other materials not described in this proposal must be treated as a change order. Please review each section of this estiamte and let us know if there are any itmes that you would like to be included.
- If it is determined throughout the project that additional work is required, we will notify you of the work needed to be performed before the work can be completed. Any additional work approved must be treated as a change order.
- Contractor and material distributor(s)/dumpster and portable toilet shall require driveway access.
- Acceptance of our contract cannot be withdrawn after JC REMODELING AND CONSTRUCTION LLC personnel appear on site ready to perform the work excepted by mutual agreement of the parties.
- All work performed within the scope of this contract will be up to code.
- Please take the necessary time to order plumbing fixtures, electrical fixtures, mirrors, vanities, ceramic tiles or any other items in order to avoid any delay/back orders. In the event that any of these items is delayed or back order and any of our subcontractors need to come back to complete their work there will be a $160 service fee added.
- The homeowner agrees for photos of the project to be taken and shared on social media. The name of the homeowner and address will not be disclosed.
- After final inspection by the homeowner, JC REMODELING AND CONSTRUCTION, LLC will not be liable for damages not related to scope of the work completed. Any repairs outside of the scopeof the work completed will involve an extra charge.